Project brief

Roof remain in situ during refurbishment works.

Demolition of rear extension and façade • strip out of floors and internal walls • Permanent steel decking and RC concrete slab • Formation of structural opening internally and externally • Above ground Temporary works • Excavation & formation of a basement to footprint and under 7m below garden level • Two/three stage Underpinning • Internal steel staircase frame • Piling • temporary works • Mass excavation of spoil • Construction of rear extension • Below slab Drainage • Cavity drain membrane Waterproofing • Insulation and screed • Pool shell

Size

3,600 sq ft

Duration

35 Weeks